Phase 6 - Consolidated Pilot

B. Consolidated Pilot: 
·   2 to 3 weeks of committed project team effort. 
·   Consists of a fully integrated system test incorporating modifications, enhancements and data conversion programs. A full "dress rehearsal" for your go live date.
·   Daily consolidated pilot scripts must be created to provide structure, organization and specific direction for all module owners.
·   Test product flow starting with demand creation and order entry, moving to planning material procurement and manufacturing and ending with shipping, invoicing, collection and review of financial results.
·   Focus your attention on the demands and constraints each module places on another as the pilot is conducted in a fully integrated environment. 
·   Project manager, module owners and project team are responsible to update and resolve the issue logs. All issue logs must be resolved prior to the completion of the consolidated pilot.
·   The ESC and project team must understand that the consolidated pilot is the proving ground for whether all systems are ready for the cutover date. If the project team conducts a successful consolidated pilot then SCL will support proceeding to the next step. If unsuccessful, SCL will evaluate the current circumstances and problems and recommend alternative plans. Action plans can vary from simply extending the pilot to allow for more testing or as complex as pushing out the cutover date in order to re-start a second consolidated pilot.

Methodology Overview
Company Information
SCL Consulting
SCL Programming
Remote Education

     

To Request More Information, Click

Systems Conversion, Ltd. -- 202 S. Erwin St. -- Cartersville, Georgia 30120 -- Phone: (770) 606-9615 -- Fax: (770) 606-9720
©2001 Systems Conversion, Ltd.