TCP/IP.
To keep cost down, eMag followed SCLs recommendation to use the
existing frame relay circuits between the 3 locations, and convert the Graham facility
over to Ethernet. This meant that eMag
could preposition and test LAN based workstations and printers. They could also forego the cost of Twinax
controllers and routers that could transmit SNA over TCP/IP.
SCL
coordinated the purchase of a new AS400 model 9406/S270 and arranged for delivery and
setup. eMag arranged to have backup
tapes sent from Texas to the Atlanta office for the initial load.
Cutover Planning
Everything revolved around the delivery
of the new AS400 and the cutover weekend was scheduled to take place 1 week prior to
period-end processing. This meant that the
window for executing this migration was just 7 business days.
The AS400 arrived exactly on the day it
was scheduled. SCL assigned a Senior
Technical Manager (STM) to the project that came on-site in conjunction with the delivery. The STM unpacked, installed and setup the AS400
resulting in a functional PRMS test environment within 3 days. That left 4 business days to complete testing of
the environment.
The Technical Team at eMag was
assigned the task of pre-positioning the LAN based peripherals at the Texas plant. Originally, the plant used Twinax impact printers. These were replaced with impact printers that
included Ethernet cards. Unintelligent
terminals were replaced with desktop PCs that ran either PRMS View, or Client Access. These peripherals were pre-positioned, installed
and tested by the Technical Team in Graham.
The
location in the UK was already using LAN based peripherals, but because of the time zone
difference, the UK was the first location up and running PRMS each day. Each location relied on the PRMS and EZPrint data
queues to print Pick Slips and Invoices. The
UK was responsible for manually starting these data queues and sometimes if the person
responsible for starting them was not available, the data queues were not started until
the locations in the United States started their workday.
This also presented problems when the European and US locations were on different
holiday schedules.
SCL
came up with a backup strategy that included the automatic starting of the data queues. This involved an extensive modification to the
programs that are usually called from the
MS0300 that prompts for the start of the PRMS data queues. Because the increased speed of the new
20Gb 7208 tape drive,
|
|
the backup program was set to save all user libraries each night. The entire process only took 50 minutes from start
to finish. This included bring the system to
a semi-restrictive state then restarting all the subsystems, processes and data queues.
The Technical team at eMag
tested various functions within PRMS and each facility Texas and the UK had
a chance to run some options from a pre-designated workstation. Everyone was amazed with the speed of the new
AS400 and was eager to see how long it took to run period-end.
Much
time was taken to document existing processes that were actively in use at eMag
Solutions. This documentation included
write-ups on how eMag secured their various environments during period-end
processing and a review of production jobs scheduled in the AS400 job scheduler.
Cutover Execution
On that final Friday morning prior to
cutover, the Technical Team in Graham took their final backups. That afternoon at 4PM, UPS packed up the tapes for
Saturday delivery in Atlanta. eMag and
SCL had their personnel on standby. When the
tapes arrived at 10AM Saturday morning, the call went out and the process of going live
went into motion.
Members of the eMag Technical
Team and the SCL STM restored the data libraries to the new AS400 and began testing. Any objects that were missing were electronically
transmitted via FTP from the AS400 in Graham. The
entire process took approximately 8 hours to complete.
The AS400 in Graham was restricted to only 3 userids to prevent a possible update
to the PRMS environment in Texas.
Late
that Saturday night, the Network Technician from eMag changed the AS400 connection
settings on the workstations in Texas and the UK to redirect them to the AS400 in Atlanta.
Post Go Live Reaction and Support
Early
Monday morning, EST, the UK started the day on the new AS400. They were pleased to see that the data queues were
automatically started and by the time the eMag Technical team came into the Atlanta
office, emails were being sent remarking on how much better the response time was and how
much faster programs were running.
|