Planning meetings began almost immediately. As a result of those
meetings, the project kickoff meeting was held in July 2000, with top management
participation from both AUTECS and SCL. Management commitment
(imperative to the success of an implementation project) was promised by AUTECS and project goals were defined:
- Upgrade to the latest
version of PRMS (version 9.0)
- Re-educate the work force
and improve system utilization
- Improve inventory accuracy
and planning reaction time
- Implement ongoing system
process evaluation and training
Education Phase
After development of a highly detailed
micro-plan for the project, SCL began the
rigorous education phase for the AUTECS
personnel. The Project Manager was key to the
project success. He constantly encouraged
everyones input and participation. The
project demands were balanced with AUTECS fulfilling its commitments to its
customers.
Education
was conducted as if the client had little or no experience with PRMS. Due
to attrition and growth, this was the case in many instances. In total, thirty classes (including some basic ERP
classes) were held over a two-month period. SCL
used the clients system, test database and products so the students would be
familiar with the data. The participants
rated each of these classes in the very good to excellent categories. They were impressed with the depth of knowledge
the consultants brought to the table, not only about PRMS, but also about how to apply
this software knowledge in a manufacturing environment such as theirs.
During
this phase of the project, AUTECS recognized
that they could be employing better manufacturing control techniques in their current
process. As a result of this discovery, the
project team, led by the project manager, recommended to management that they should make
the change from a discrete environment to a repetitive environment during the cutover to
the 9.0 version. The management team agreed
with the need for this change. It would be
incorporated in the scope of this project.
Piloting Phase
Piloting
is where education theory and real-world application come together. AUTECs project team
|
|
members got hands-on experience setting up
the system, loading their data, and utilizing the tools as if they were in their live
environment. Real enlightenment resulted as
the team members made one discovery after another.
Piloting
is also the phase were the SCL technical team
became significantly involved in the project. By
this time, the project team had developed a very good understanding of what PRMS could
provide and what modifications would be needed to improve its applicability to their
specific business processes. Modification
requirements were listed and prioritized, determining what must be done before the cutover
and what could be done during post-implementation. SCLs technical resources were assigned
accordingly.
By
the time the Consolidated Pilot was to begin, SCLs
project manager had sufficiently weaned himself away so that the project team
members could function as the module experts during this phase.
Additional
AUTECS employees were brought into the training
environment and taught how to perform their daily duties by the AUTECS module leaders. SCL
supported AUTECS throughout this phase whenever
problems arose or clarification was needed. However,
AUTECS was clearly in control of their project
at this point.
Technical
commitments were completed, and the entire process, including third-party applications,
was repeatedly processed to assure a smooth functioning system had been designed and
built.
Cutover Planning
Cutover
Planning involved preparation for the actual cutover date.
A majority of this project phase involved data-conversion planning. All programming modifications that were required
prior to cutover were implemented and tested. SCLs
technical consultant assigned to the project wrote specific data conversion tools to deal
with the evolution from discrete to repetitive manufacturing during the cutover. The micro-plan was further expanded to include a
highly detailed cutover plan incorporating a step-by-step guide for each cutover or
data-conversion activity. This document alone
listed more than 200 activities that would be performed during the cutover.
An
entire weekend was planned for the cutover. At
the close of second shift on a Friday night in December, the cutover plan was executed,
checking off each step one-by-one to assure
|